Jaana Koivuniemi – Finland

I have worked at Robit for ten years now, starting out as a summer employee, and currently I work in the packing section.

What I like best about my job is my great colleagues and the variety of my duties! Although the morning shifts are busy, even hectic, I still enjoy it.

And the day brings its challenging moments, too: in the middle of all the hustle and bustle, it’s important to keep a cool head to ensure the right order gets to the right destination. There are so many different types of models of all the products that it is easy to mix them up if the orders are not given 100% focus.

Robit is a really great place to work, and I appreciate that they take care of the well-being of their employees. The cultural vouchers, for example, are fantastic! I’m very happy to be recognised with the title of Production worker of the year 2013.

After a well-managed work day, I like to relax at home with my good-natured English bulldog.

Sang Hee Kim – South Korea

The South Korean unit’s production employee of the year 2015, I am a materials engineer and work at Robit’s Donghae plant.

After graduating from university, I worked in electronics and construction, among other jobs. That helped me when applying for a job at Robit, as did my studies in materials engineering, which also involved learning about drill rigs.

I am a CNC operator and I have held a couple of different positions during my five years here. We are like one big family, which is really nice. If I have a problem, my colleagues are always willing to help me resolve it.

Regarding my responsibilities, as a CNC operator, I am focussed on developing my skills and constantly improving in my job. I have been learning particularly about CNC programming, and someday I will be a CNC master.

As for my spare time, my hobby is currently playing with my six-year-old. And if I can find the time, I would really like to play tennis, practice fencing and go fishing.

Sun Mi Kim – South Korea

I am an Administration Coordinator and have worked at Robit Korea Ltd since autumn 2010. My responsibilities include assisting with bookkeeping, calculating the payroll, purchasing tools and miscellaneous goods, and managing inventories.

I am responsible for employee attendance management and financing. At the start of the month I go over the due dates, for example, for bookkeeping, payroll and sales.

A diligent worker, I always put 100% into my work – whether the task is big or small.

I hope that I will have further development within the company and would like to work for a long time. I previously graduated from Kangwon National University.

In my spare time, I enjoy watching movies and rollerskating.

Anssi Lehtinen – Finland

I started working in production at Robit’s Lempäälä plant in 2011. I work with ground drilling products, and my tasks include inserting carbide buttons and pressing and operating the blackening line. I like having diverse job roles.

My diverse tasks and nice colleagues are definitely the best part of my job. The most challenging thing is managing my sleep cycles in three-shift work.

In my free time, I go fishing, play billiards and grow chili peppers. I consider Robit a reliable and flexible employer, and I was happy to be chosen as Production Employee of the Year. Of course it’s nice to hear that my efforts at work are appreciated.

Jinman Kim – South Korea

I am a production team shift supervisor at the Donghae factory in Korea. I had been working for YP-CND since the early 2000s and became a Robit employee after Robit acquired YP-CND in 2011.

My typical working day consists of managing a number of things at the factory site, such as shift employees, machine maintenance, allocating machine resources, CNC programming, et cetera.

What I like best about my job is that it gives me great satisfaction to see something that has so far only been an imaginary drawing turn into a real object in a machine. I also enjoy training and learning about new machines and systems.

As for spare time, we are very busy at the Korea factory these days and it’s not always easy to find spare time. But when I do, I like to take a walk by a nice little river near my home or go hiking in the mountains.

Stephen Straw – UK

I am a CNC machinist at Bulroc Robit UK, Chesterfield. I have worked for Bulroc for some 30 years.

My day-to-day work mainly consists of programming and operating various CNC lathes. I specialise in manufacturing the larger hammer and one of our special orders. I enjoy working on new production projects and it gives me great satisfaction when the new product works correctly.

Bulroc was acquired by Robit about a year ago. Has that changed anything?

Since the takeover I have seen numerous changes in the form of new machinery and other investments, bringing us more up-to-date and in line with our competitors. Also, the health and safety implementation have made the workplace a safer place to be.

In my spare time I like to visit and keep in contact with my family who mainly live away. I have hobbies such as golf, keeping fit and walking my dog. I also enjoy having a good bottle of wine with friends.

Minna Turpeinen – Finland

I joined Robit in 2005.

I started as a metal worker in 1994, making, for example, springs. Currently I spend a large part of my working day at Robit by the furnace, inserting buttons and carrying out the related measurements. During my time as shift supervisor, I make sure that the required products are made on time, and I am responsible for the work order. In addition, I am the industrial safety delegate for the employees. Shift supervisors are also responsible for receiving goods and for the work arrangements of their shifts. Their efforts have a considerable influence on our delivery reliability and on work efficiency.

The best thing about my job is definitely my nice and hard-working colleagues! I like being able to work independently. The changing workdays are also a big bonus. The most challenging aspect of my job is figuring out how to squeeze all the things I plan to get done into my 8-hour shift! (laughing). In spring and autumn I spend my free time berry- and mushroom-picking. Fishing is also fun, although nowadays I don’t have much time for it. I do handicrafts whenever I can find the time.

TGB and Robit made the “impossible” sheet piling possible

Overview

A Swedish company TGB had major difficulties in sheet piling through rocky boulders. With Robit’s pilot technology, the impossible was made possible.

The rocky terrain proved to be so challenging, that the company decided to pre-drill the holes with Robit® Multi-Use casing system and retrieve the casing (406.4/12.5; L=6000 mm) afterwards. In the same project some piles were permanent and with the Robit® DTH-RoX 3-1, the same pilot was used to complete the drilling with Eco-rings.

TGB was able to complete the project on time with controlled investment. Christer Wretman, our distributor in Sweden, says: “Impossible project was turned to success with Robit Casing System”.

Skanska and Robit kept a warehouse stable in Turku

Overview

To meet the demands from the contractor, Skanska needed new drill technology for reinforcing the foundations of a famous warehouse with underpinning.

A long-time landmark in the center of Turku, Sokos Wiklund warehouse building, needed a total of 200 holes to be drilled with casing in the underground parking hall. Additional corrosion reinforcement and concrete were then installed inside the 219.1/12.5 Ruukki casing tube. Due to space restrictions set by the site, a small drilling unit was used. Drilling with a ring bit casing system was the only alternative.

With Robit Casing System, the drilling was completed in a very short time. With such an impressive outcome, it was decided to introduce the system to several similar projects in the region.

Robit and Sotkamon Porakaivo anchored a paperi mill to the bedrock

Overview

A paper mill in Finland needed altogether 58 holes for foundation reinforcement with depth varying from 12 to 16 meters. The terrain over bedrock was difficult, but Robit Casing System handled it fine.

Sotkamon Porakaivo had a challenge with the job of casing drilling to the bedrock and then drilling one meter into the bedrock itself. The first six meters of the formation consisted of sand and gravel. Blocks of granite and grillage (wood, clay and gravel) had also to be dealt with.

Robit® Casing System was the preferred technology due to its ability to drill difficult formations. Casing tube of 139.7/5.6; L=3000 mm was used. A 90 mm diameter steel bar was inserted and grouted to each hole. The end result was that the drilling went smoothly despite the difficult drilling conditions.

Pipe pile wall construction work at Viljuisk hydro power plant in Yakutia Russia

Overview

The goal of this project is to secure the reinforced concrete bottom and wall slabs of the incoming water channel and also to prevent their final breakage and flushing away by water flow.

The project owner is Russian State energy company «Rushydro» and it is projected by OAO “Lenhydroproject” engineering company from St. Petersburg in cooperation with Robit Rocktools. From Robit´s side the project was supported by Mr. Kari Juntunen and Mr. Juha Sorjonen. The project also included underwater drilling which was made during the operation of hydro power plant.

The project included the following stages:

  • diving operations in the depth of 8-9 m with water flow rate of 0,5 – 1,0 m/s
  • drilling through 1,7 – 1,95 m reinforced concrete bottom slabs using 1 m diam. diamond bit
  • removal of 1 m diam. pieces of reinforced concrete slab from the bottom
  • construction of 720 mm pipe pile wall (height 11,5 m) on the river bottom through the drill hole in reinforced concrete slab
  • concreting of the seam between the reinforced concrete slab and pipe pile wall
  • underwater concreting and installation of the pipe pile wall on the whole length of channel

After the operations above the complete pipe pile wall is installed according to the cross section of the incoming water channel of hydro power plant. This construction is used to prevent the breakage and flushing away of reinforced concrete bottom slabs what has already taken place during the last 20 years of operation.

Time of the project is 2 years but due to the working schedule of the power plant surface and underwater operations can be commenced only in July – September.

The installation of pipe pile wall was started in July 2013 by contracting company “OOO SU-299” from St. Petersburg. Till the end of September 15 piles were drilled and 20 m of pipe pile wall was installed. The method has proved to be successful and economical in the extremely hard working conditions of Yakutia.

From “OOO SU-299” company the project was managed by Mr. Vitali Korshunov, Project Manager and Mr. Vladimir Klimov, Development Director.

The following machinery was used in the project:

  • “BRAUN” diamond drilling equipment and tools
  • “ROBIT ROCKTOOLS” drilling technology and tools, Wing Bit DTH SF 720/10 N180
  • “COMACCIO” DTH drilling rig
  • “ROBIT” 18” DTH hammer
  • 200 t and 500 t barges, floating crane 5 t , a towing vessel

 

Piling without disturbing the neighbours in Stockholm

Overview

Solna Arenastaden right next to Solna railway station needed support piles for passage over railway between Arena and surrounding buildings. The urban site called for extra care and Robit products.

The work site needed some 150 piles (220/12.5) to be driven to overburden ground, which tends to ”suck the water” due to numerous fractions. What’s more, there was a large sewage passing near the worksite, let alone railway and buildings. In this environment, any pollution would be no-no as well.

Due to ground type, air drilling would almost surely cause problems to surroundings. The use of Wassara W150 ensured fast penetration and created less noise. The project was finished with minimum disturbance.

New Robit horizontal drilling equipment proves its worth in Sweden

Overview

Robit, in collaboration with our retailer Swedish retailer GDS Sverige AB, put our new HZ product series to test under a motorway ramp near Landvetter airport.

Robit has been developing the new HZ series for horizontal drilling in Sweden since the early 2011. Now, the new system was put through its paces under a motorway ramp, where a 24-meter hole of size 406.4/12.7 was drilled. The land filling under the ramp consisted partially of very large boulders. Because of the boulders and directional requirements, the drilling was a challenging test to our new HZ series.

Despite the rough terrain, the results proved successful. No problems occurred, and the drilling went as

planned. What’s more, the test drilling results have enabled the company to further improve the functionality of the HZ product line.

Lemminkäinen builds a new metro station with Robit

Overview

The so-called West Metro is a major expansion to current underground railway system in the Finnish metropolitan area, stretching it all the way to Espoo. Lemminkäinen is in charge of building the Koivusaari metro station, complete with a kilometer of tunnel. As usual, Robit delivers the goods.

The project, involving much earth-moving and digging, takes place in an urban, unforgiving environment. “The location is challenging, so it is essential that all components needed for the work have high quality and reliability”, says Annina Peisa, Construction Manager at Lemminkäinen. “Our suppliers have a substantial impact on the success of our projects”.

Lemminkäinen and Robit have been co-operating successfully for the past ten years, and this site is no exception. The installation and drilling tools required for making excavations and supporting the walls with RD piles this are supplied by Robit. Thanks to our dedicated, knowledgeable service, the construction is well on the way, and expected to be finished on time.

No wonder Peisa is pleased: “Robit is a very customer-oriented partner”, she says. “If we have any problems in our projects, Robit will provide us with quick and professional service. They will come and check the situation on site as needed.”

Customer description

Lemminkäinen is a construction group specializing in building construction, infrastructure construction and technical building services. Its main markets are Finland and the Baltic Sea region. The Group employs about 8,400 people, and its turnover in 2011 was approximately EUR 2.2 billion.

Trading in Robit Plc’s shares on Nasdaq Helsinki Ltd’s official list commented today

Trading in the shares of Robit Plc commenced today, 17 May 2017, on the official list maintained by Nasdaq Helsinki Ltd.

“The past two years as a public company have proved that Robit has successfully implemented its strategy. Since the listing, Robit has continued to grow organically and through acquisitions allowing the company to take a step towards “Robit 3.0″ growth phase Nasdaq Helsinki Main market company. We are very proud of Robit’s achievements and ready to continue implementing our growth strategy. The targets of entering the main list are to increase the awareness of the company and improve the liquidity of the share as well as to reach new owners. Entering the main market of Nasdaq Helsinki is part of the company’s growth and strategic development”, says Harri Sjöholm, Chairman of the Board of Directors of Robit.

Violetta Hünninen
IR & Communication

Lemminkäinen and robit provide underground parking for 900 cars

Overview

A world-class parking facility called Kivisydän (“Heart of Stone”) is currently being excavated by Finland’s leading underground construction company, Lemminkäinen Corporation at a depth of 30 meters beneath Oulu’s city center. One of the largest and most challenging of its kind in Finland, the project makes good use of Robit’s expertise.

Robit Rocktools Ltd and Lemminkäinen have worked in close co-operation for nearly a decade, mostly in ground drilling. Kivisydän is the companies’ tunnel excavation pilot project. “The project extends our good partnership to the area of tunnel construction. Robit is supplying us with the latest technology button bits needed to excavate the underground parking facility. They are also taking care of sharpening the bits,” says Pentti Nieminen, site manager from Lemminkäinen.

Construction and excavation in the downtown core sets special demands on the work and planning. “This is a challenging underground site” emphasizes Pentti Nieminen. “We need expert partners whose work we can trust explicitly. In demanding conditions, knowledgeable people and state-of-the-art equipment are crucial for success”.

Robit’s trump card is, in addition to high-quality products, the smooth integration of a bit-sharpening service with deliveries. “Thanks to the service, our cooperation partners don’t have to worry about servicing the bits. This allows them to focus completely on their core competence,” explains Timo Rajala, Robit’s Finnish Sales and Marketing Director.

Robit helps the 2014 olympic games happen in sochi

Overview

In the course of the years, Robit Rocktools Ltd has been involved in several Olympic Games building projects all around the world. The work will continue with the next Winter Olympics in Sochi, as the local contractors rely on Robit products for digging the tunnel network – a necessary part of the game venue infrastructure.

The 2014 Olympic Games will be organized in Sochi, the first Winter Olympics to be held in Russia. To ensure smooth transport between the various sites, a tunnel network with a total length of over 26 kilometers is being excavated in the area. One of the key factors behind Sochi’s selection as the Olympic City was the creation of a functional road and railway network, and Robit has its share in this.

Several contractors in Sochi are utilizing the Robit RoX+ 88.9/8 Top Hammer system in tunnel work. The system consists of a pilot bit automatically locking with a ring bit, which makes work considerably easier and faster. “Word about the excellence of our product quickly got around the Sochi sites, and a total of six contractors started using it”, says Oleg Ivanov, Regional Manager at Robit Rocktools Ltd.

“Our co-operation went smoothly. The contractors appreciated our proactive technical support and service. We were able to respond to their wishes comprehensively,” Ivanov continues. Work on the Sochi tunnel sites is getting near completion. “We will continue by delivering our HTG bits to the Olympic sites as needed.”

Metro heads to the west with Kalliorakennus and Robit

Overview

The challenging construction work of the new, westbound metro line in Helsinki demands wide-ranging expertise. Drilling maintenance shafts for metro tunnels has little room for error, but Kalliorakennus-Yhtiöt ensured a successful end result by using Robit products.

The metro tunnel shafts are a vital part of the underground railway system. They serve as emergency exits, smoke vents and pressure equalization as well as ventilation systems. Among their other large contributions to the West Metro construction, Kalliorakennus-Yhtiöt had to drill 44 meter-deep shafts with a surface area of 68 square meters to solid Scandinavian bedrock – by no means a trivial task.

“We set tough quality requirements for the project, as the work outcome must be exact. We drilled the excavation holes for the shaft from the top right down to the bottom, whereas drilling is normally carried out from both the bottom and the top. It was crucial that the holes turned out straight,” explains site manager Martti Kähkönen from Kalliorakennus. “We used Robit Rocktools special equipment to make sure the drilling holes were straight”.

The collaboration between Kalliorakennus and Robit go back since the early ‘90s. “All of the bits we use are from Robit, because they are familiar products for me. I participated in the bit development work for the first time many years ago”, Kähkönen recalls. In addition to the shared history, Robit’s wide service offering has also impressed Kalliorakennus. “Robit is a reliable partner, but their bit-sharpening service was also a major reason behind why we chose them as co-operation partner in the West Metro project,” he says.